HomePremier Contributes to BGE’S Electric Reliability Investment InitiativeUncategorizedPremier Contributes to BGE’S Electric Reliability Investment Initiative

Premier Contributes to BGE’S Electric Reliability Investment Initiative

In partnership with North American General Contractors, Premier Concrete is working on a multiphase project for Baltimore Gas and Electric (BGE). This project aims to convert a portion of the Fallsway Properties LLC parking lot into a new 155 kV switching station for BGE.

In phase one of this project, Premier will be working on the cable vault and the responsibilities include installing stone under the mat formation, furnishing and installing concrete reinforcing, constructing concrete walls, installing embeds, and applying topping slab. In the second phase of the project, Premier will be completing site work; responsibilities will include constructing drilled pier foundations, installing ramp foundations and a wall, and working on the 1,817-square-foot sidewalk along Constitution Street.

The project is a sub-part of BGE’s Electric Reliability Investment Initiative. Under this initiative, BGE is also working on other projects in the local area that will improve the electric distribution system. These improvements will help BGE upgrade the services they provide to Baltimore City customers by minimizing the frequency and duration of time that electric service is disrupted for their customers.

Construction for this project began in February 2015 and the construction is not scheduled to end until December 2015. To learn more about this project visit BGE’s website.